ANALISIS SISTEM PENGENDALIAN BIAYA (COST CONTROL FRAMEWORK) PADA PROYEK PELEBARAN JALAN SP.3 LEMPAKE SAMARINDA - SP.3 SAMBERA KALIMANTAN TIMUR

Authors

  • Edward Prana
  • M.Ruslin Anwar
  • Yulvi Zaika

DOI:

https://doi.org/10.22219/jmts.v10i2.1785

Abstract

Edward Prana1, M.Ruslin Anwar2 & Yulvi Zaika3

1,2 & 3Fakultas Teknik Jurusan Teknik Sipil Universitas Brawijaya Malang
Alamat Korespondensi: Jl. MT. Haryono No 167 Malang, Indonesia
e-mail: edwarprana@ymail.com

ABSTRACT

In this study, will be analyzed Cost control framework on one road construction project in
East Kalimantan using Earned Value Concept and Work Break Down Structure. As the object of
study is Sp.3 Road Widening Project Lempake (Dublin) - Sp.3 Sambera located in the city of
Samarinda, East Kalimantan. way of acquiring primary data through observation and interviews
directly to the project, while secondary data from project documents.
Performance costs and time by using Earned Value Concept in terms of the reporting week 25
CV and SV value value Positive Negative, indicating that the work has been delayed from the time
the work plan, but the cost is still below the budgeted costs. Resource use efficiency using Earned
Value Fund at week-25 values of 1.11 and SPI CPI of 0.93. Cost performance, while showing
good performance for performance efficiency by less well because of a delay of the planned time.
Predicted cost and project completion time estimated the cost for the remaining work on the
assumption that the trend of the performance of the project will remain until the end of the project
(ETC) amounted to Rp 3, 138,305,144.17 while the estimated cost of up project completion (EAC)
is equal to = Rp. 9,871,988,500.07, which means there is no advantage or still under the budget plan
(PV) in the amount of Rp. 10,968,876,111.19. While the estimated schedule for the completion of
the aspects of the job completion time estimates obtained (TE) assuming the performance trend of
the project remains is 212 days. This means that the project will be delayed approximately 14 days
of 198 days plan.

Keywords: Control cost (Cost control framework), Work Break Down Structure, Earned Value
Concept.

Downloads

Download data is not yet available.

Downloads

Published

2014-03-05

Issue

Section

Articles