ANALISA BIAYA DAN WAKTU DENGAN MENGGUNAKAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN HOTEL ASTON PARAMOUNT MALANG
DOI:
https://doi.org/10.22219/jmts.v12i1.2039Abstract
ANALISA BIAYA DAN WAKTU DENGAN MENGGUNAKAN
METODE TIME COST TRADE OFF PADA PROYEK
PEMBANGUNAN HOTEL ASTON PARAMOUNT MALANG
Iktiva Sani1, Zamzami Septiropa2
1,2Jurusan Teknik Sipil Fakultas Teknik – Universitas Muhammadiyah Malang
Alamat korespondensi : Jalan Raya Tlogomas 246 Malang 65144
ABSTRACT
Implementation of Development Projects Aston Paramount delayed completion time caused
by the discharge of water continuously from the underground, thus flooding the area GWT (Ground
Water Tank), STP (Sewage Treatment Plan) and the destruction of Tower Crane. It can be based on
time schedulle project in November 2012 or at the time the project reaches 17 weeks, the progress
of the plan should reach 28.648%, but the reality on the ground has reached 24.194%, so it can be
known deviation -4.454%.
The method applied in this thesis Time Cost Trade Off (TCTO) to speed up implementation of
the project in order to achieve the optimum time in the rest of the work project. TCTO a time and
Biya exchanges with a view to speeding up the duration.
Acceleration time is done by holding the shift work. Of the project schedule has been delayed,
the rest of the project is completed within 180 days for a total cost of Rp. 32,679,810,571.24.
However if the project accelerated by using TCTO to return to the original plan schedule is 162
days obtained a fee of Rp. 33,462,446,260, the difference between the cost of Rp. 782,635,689.88.
Keywords: Time and Cost
Downloads
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2014 Iktiva Sani, Zamzami Septiropa
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).
MEDIA TEKNIK SIPIL Journal
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.