ANALISA BIAYA DAN WAKTU DENGAN MENGGUNAKAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN HOTEL ASTON PARAMOUNT MALANG

Authors

  • Iktiva Sani
  • Zamzami Septiropa

DOI:

https://doi.org/10.22219/jmts.v12i1.2039

Abstract

ANALISA BIAYA DAN WAKTU DENGAN MENGGUNAKAN
METODE TIME COST TRADE OFF PADA PROYEK
PEMBANGUNAN HOTEL ASTON PARAMOUNT MALANG

Iktiva Sani1, Zamzami Septiropa2

1,2Jurusan Teknik Sipil Fakultas Teknik – Universitas Muhammadiyah Malang
Alamat korespondensi : Jalan Raya Tlogomas 246 Malang 65144

ABSTRACT

Implementation of Development Projects Aston Paramount delayed completion time caused
by the discharge of water continuously from the underground, thus flooding the area GWT (Ground
Water Tank), STP (Sewage Treatment Plan) and the destruction of Tower Crane. It can be based on
time schedulle project in November 2012 or at the time the project reaches 17 weeks, the progress
of the plan should reach 28.648%, but the reality on the ground has reached 24.194%, so it can be
known deviation -4.454%.
The method applied in this thesis Time Cost Trade Off (TCTO) to speed up implementation of
the project in order to achieve the optimum time in the rest of the work project. TCTO a time and
Biya exchanges with a view to speeding up the duration.
Acceleration time is done by holding the shift work. Of the project schedule has been delayed,
the rest of the project is completed within 180 days for a total cost of Rp. 32,679,810,571.24.
However if the project accelerated by using TCTO to return to the original plan schedule is 162
days obtained a fee of Rp. 33,462,446,260, the difference between the cost of Rp. 782,635,689.88.

Keywords: Time and Cost

Downloads

Download data is not yet available.

Downloads

Published

2014-11-03

How to Cite

Sani, I., & Septiropa, Z. (2014). ANALISA BIAYA DAN WAKTU DENGAN MENGGUNAKAN METODE TIME COST TRADE OFF PADA PROYEK PEMBANGUNAN HOTEL ASTON PARAMOUNT MALANG. Media Teknik Sipil, 12(1). https://doi.org/10.22219/jmts.v12i1.2039

Issue

Section

Articles