Minimasi Maskepan Dengan Penjadwalan Produksi Pada Tipe Produksi Berulang

Authors

  • Imron Kuswandi

DOI:

https://doi.org/10.22219/JTIUMM.Vol11.No1.84-93

Keywords:

production scheduling, makespan minimation.

Abstract

Methodologically there are some problems in the methods of scheduling production which
have been available. In the methods of scheduling production which have been available, it is
often less capable for giving the real condition images from the real systems. It is indicated by
the given assumption that each operation should be finished previously before the other operations
are done. This case is inappropriate if applied in the repetitive production types as happened
in X Gresik, Co. Ltd. Because methodologically there are some problems in the methods
of scheduling conventional production, so in this research the methods of scheduling conventional
production are modified by using Microsoft excel application software, so it enables in
this method to handle the case of scheduling production in the types of repetitive production.
urthermore, by using the methods of scheduling production modified by using Microsoft excel
application software, the scheduling can be achieved by the better makespan (makespan =
471,17 hours), so the production facility utilities are also more optimal compared to production
scheduling results by conventional approach (makespan = 893,7 hours).

Downloads

Download data is not yet available.

Downloads

Published

02/18/2012

How to Cite

Kuswandi, I. (2012). Minimasi Maskepan Dengan Penjadwalan Produksi Pada Tipe Produksi Berulang. Jurnal Teknik Industri, 11(1), 84–93. https://doi.org/10.22219/JTIUMM.Vol11.No1.84-93

Issue

Section

Article